Endicott Station has been a construction site since the week of June 15. The last disruption before its new platforms open is set for the first weekend of November. Under the Town of Dedham's current plan, the station closes partly on Friday, November 6, and fully on Saturday, November 7. The new mini-high platforms are projected to enter service on Thursday, December 3.
The closure is the MBTA's plan, but the dates aren't posted on the MBTA timetable. They're on the Town of Dedham's Endicott Station project page, last updated October 5. On the MBTA side, the Franklin/Foxboro Line is running one construction schedule now and switches to another on November 10. If you board at 186 Grant Avenue, the next six weeks depend on reading both calendars together.
Three Clocks Running at Once
Here's the full sequence, from the schedule change on Monday, October 26, to the platform opening:
- Monday, October 26. The MBTA's Fall/Winter commuter rail schedule took effect, and every train number changed to four digits. The Franklin/Foxboro Line stayed on a construction schedule for ongoing track work, with some departure times adjusted.
- Friday, November 6. Endicott partly closes after the morning rush, starting after 8:30 a.m. Work pauses for the evening rush at 5:30 p.m. and resumes outside those hours.
- Saturday, November 7. The station closes all day for platform work and paving of the pedestrian crossing.
- Monday, November 9. Projected substantial completion of the project. This is also the last day of the Franklin/Foxboro construction schedule that began October 26.
- Tuesday, November 10. A new Franklin/Foxboro construction schedule takes effect.
- Thursday, December 3. Projected date for the new platforms to enter service.
Look at items four and five. The weekend closure falls in the final days of one construction timetable, and the next timetable starts the day after the project is meant to wrap up. Your regular train on November 6 may not leave at the same time on November 12. The MBTA has posted both PDFs on its Franklin/Foxboro timetable page, and you can compare them line by line before the switch.
Why the Timetable Still Shows Trains Stopping on November 7
If you open the MBTA timetable for Saturday, November 7, you'll still see some trips scheduled to stop at Endicott, while other trips that day are marked as skipping it. That doesn't match the Town's description of an all-day closure. The MBTA's Endicott alert hasn't caught up either. It was last updated September 11 and describes only path changes and daytime construction "through the Winter of 2026." It doesn't mention the November closure, replacement buses or an alternate station.
The Town's page explains the gap. It says the MBTA will share rider information through its website and mobile app, so that's where closure details should show up as the date gets closer. In the meantime, treat the Town's dates as the plan of record. Check the MBTA Franklin/Foxboro alerts page or the app before you leave on the 6th or 7th.
There's another MBTA alert on the commuter rail alerts page, and it isn't about Endicott. Buses will replace Foxboro Line service between Foxboro and Walpole on Friday, November 6, and Monday, November 9, connecting with Franklin Line trains. That affects the Foxboro branch only, even though it lands on one of the Endicott closure days.
What the Work Has Already Built
November is the end of a project that has mostly stayed on schedule, and sometimes beat it. Since construction began in June, the Town's updates have recorded these milestones:
- August. Site setup was finished, and excavation and concrete foundation formwork were underway. Concrete footings and underground electrical work were underway on the platform side, and civil access work was continuing on Depot Street.
- Early September. The two ADA parking spaces closed on September 4 to store canopy materials. The inbound pedestrian ramp closed on September 8 for about five weeks while it was rebuilt to meet ADA standards. A temporary accessible path stayed open, and so did the inbound stairs.
- September 8 to 21. Crews worked overnight between 1 and 5 a.m. to install the steel for the new canopies, starting on the inbound side and moving to the outbound side on September 15.
- September 16. Canopy installation finished, five days ahead of the original schedule.
- October. The plan called for finishing the platform surface and building the pedestrian ramp in the station parking lot.
The project also goes beyond the platforms. The Town lists a regraded parking area, a regraded sloped walkway at the end of Elmwood Avenue to meet ADA standards, and rebuilt sidewalks on both sides of Depot Street. It also mentions better lighting and pedestrian access. If you live on Depot Street or Elmwood Avenue and have never taken the train, these are the changes that reach your front door.
What Changes on the Platform After December 3
The MBTA runs three kinds of commuter rail platforms. A full high-level platform gives level boarding at every car. A low-level platform means stepping up into the train. Endicott is getting the middle option, the mini-high, on both the inbound and outbound sides.
| Platform type | Level boarding at | How it works |
|---|---|---|
| Full high-level | All cars | Board from any door |
| Mini high-level | 2 cars | Stand on the mini-high before the train arrives, and the operator assists |
| Low-level | None | Step up from platform height |
According to the MBTA's Commuter Rail Access Guide, mini-high platforms usually connect to the low-level platform by a ramp. Riders who need level boarding should be standing on the mini-high before the train pulls in. At both full high-level and mini high-level platforms, conductors can put down a bridge plate on request to cover the gap between train and platform. That makes the new Endicott a station where your spot on the platform matters. For stroller riders, travelers with heavy luggage and anyone using a mobility device, the raised section is the place to wait.
December 3 is a projection, and the Town says finishing work may continue into 2027. Its project summary says the platforms are expected to open "this winter," with a final timeline still to come from the MBTA project team.
The Dedham Weekends Around the Work
The station calendar overlaps with a busy stretch in Dedham Square. The Saturday after the closure, November 14, Dedham Square Circle starts its indoor Winter Farmers Market at Dedham First Church & Parish, 670 High Street, from 10 a.m. to 1 p.m. The next market is December 12, and monthly dates are already posted through March 2027.
The day after the platforms are projected to open, Friday, December 4, Dedham Square Circle hosts its Holiday Stroll & Gift Market from 5 to 8 p.m. Plans include more than 30 street vendors, a free Holiday Train display from the Dedham Museum & Archive, and the lighting of the Town's Christmas tree at 6:30 p.m. Starting at 4:30 p.m., High Street closes from Washington Street to the Harris Street intersection, and Eastern Avenue closes from High Street to CVS. The Town parking lot stays open.
If you're driving home that Friday, those Square closures land in the evening rush, one day after Endicott's projected return to full use. As with November 6 and 7, check the station status on the MBTA app before you count on it.
Station upgrades like this one shape how buyers see the streets around them, and I keep track of that change block by block. If you own a home near Depot Street, Elmwood Avenue or Grant Avenue and want to know how it compares in today's market, Elena Price can help. Request your Instant Home Valuation.